BE36: Pushover Analysis: Performance Point Calculation by ATC-40 Procedure
The following example is intended to verify the ATC-40 procedure for the calculation of the performance point (illustrated schematically in the figure), as implemented in SOFiSTiK. The elastic demand and capacity diagrams are assumed to be know.This is one example of our Verification Manual. You can find the whole manual in SSD and TEDDY via menue Help > Verification Manual, the input data files in TEDDY via menue Help> examples... > verification.